SCADA system RC1 reached the age of majority!

18th anniversary of the first SCADA system RC1
SRC SOFT celebrates 10 Years of Business

May 2011

SRC SOFT celebrates 10 years of successful bussines

2011 marks the 18th year since the first SCADA system RC1 was commissioned, in substation 35/10kV Jasen, Konarevo

April 2011

Completed development and testing new version of RC1 SCADA V3.34

March 2011

AD Elektro Doboj - Commissioned controllers for connecting modified reclosers with built-in SEL-551C relay to System RC1.

AD Elektro Doboj - substation computer in TS 35/10kV Blatnica and TS35/10kV Šamac 1 connected to SCADA system RC1 via Ethernet connection using protocol IEC60870-5-104.

February 2011

ED Valjevo - delivered 5 pcs of integral uninteruptable power supplies for radio stations - RC-NPB150

January 2011

AD Elektro Doboj - completed delivery of 23 controllers for connecting modified reclosers with built-in SEL-551C relay to System RC1.

December 2010

ED ELEKTROMORAVA Smederevo - delivered digital voice recording device Registrofon RC3.

ED Pirot - delivered and commissioned equipment for TS 35/10kV Babušnica 2 and TS 35/10kV Dolac: signal interfacing, distributed RTU and substation computer. Substations are connected to SCADA system ED Pirot via radio link, using protocol IEC 60870-5-101.

AD Elektro Doboj - delivered digital voice recording device Registrofon RC3.

November 2010

ED Šabac - delivered 3 pcs of integral uninteruptable power supplies for radio stations - RC-NPB150.

October 2010

We participated as an exhibitor on expo part of VII Conference on electricity distribution for Serbia and Montenegro, CIRED 2010, from 26. september to 01. october 2010., in Vrnjačka Banja.

September 2010

PD Elektrosrbija Kraljevo - delivered 20 pcs of integral uninteruptable power supplies for radio stations - RC-NPB150 and 10 pcs off power suplies for radio stations with DC input voltage RC-NPJ150.

August 2010

Serbian Railways - delivered 8-channel digital voice recording device Registrofon RC3 with uninterruptible power supply of prolonged (12h) autonomy. Device will be installed at Railway-station Zrenjanin.

July 2010

TE Nikola Tesla, Obrenovac - delivered 4-channel digital voice recording device Registrofon RC3 with alarm unit.

ED Prokuplje - delivered 4-channel digital voice recording device Registrofon RC3.

May-June 2010

Completed development of a new generation of controllers for uninterrupted power supply. Controllers will be installed in integrated uninterruptible power supply RC NPB150.

Completed development of a complete family of modular communications converters that provide galvanic separation and conversion of signals between different types of interfaces.

April 2010

Completed development of a new universal mini remote terminal unit for SCADA system RC1. The new device can be used as a standalone remote station of limited capacity for connecting smaller structures in the SCADA system, or as a part of distributed remote station RC1, for incorporation into individual cells within a large substation.

March 2010

ED Vranje - Delivered and commissioned mini remote station in RP 10kV Sveta Petka, Klenike. The station is connected to SCADA system RC1 ED Vranje.

Released new version of software for communication gateways connecting TAVRIDA reclosers to SCADA system RC1. This version covers the changes that were done in recloser firmware release 6661.

February 2010

ZEDP Elektro-Bijeljina - RC3-GM16A, 16-channel digital voice recording system with automated voice response, delivered, installed and commissioned.

AD Elektro Doboj - completed delivery of 20 controllers for connecting modified reclosers with built-in SEL-551C relay to System RC1.

January 2010

Completed development of a new uninterruptable power supply 600W/1000VA with up to 24 hours of autonomy. The first unit will be shipped to ZEDP Elektro-Bijeljina within delivery of voice recorder RC3-GM16A.

December 2009

Serbian Railways - completed installation and commissioning of 11 devices of digital voice recording system Registrofon RC3 at the following locations:

  • Railway-station Novi Sad - 24 channels
  • Railway-station Ruma - 16 channels
  • Railway-station Belgrade - 12 channels
  • Railway-station Nis - 12 channels
  • Railway-station Vrbas - 12 channels
  • CDU (Center for Remote Control) Nis - 8 channels
  • Railway-station Sid - 8 channels
  • Railway-station Indija - 8 channels
  • Railway-station Stalac - 8 channels
  • Railway-station Kraljevo - 8 channels
  • Railway-station Mala Krsna - 8 channels

November 2009

AD Elektro Doboj - substation computer in TS 35/10kV Usora connected to SCADA system RC1 via Ethernet connection using protocol IEC60870-5-104.

For the purposes of AD Elektro Doboj realized controller for connecting modified reclosers with built-in SEL-551C relay to System RC1. It will be delivered 20 controllers.

October 2009

ED Valjevo - delivered 8 pcs of integral uninteruptable power supplies for radio stations - RC-NPB150.

July 2008
ED Kraljevo - substation computers in TS 110/35/10kV KRALJEVO 2 and TS 35/10kV FABRIKA VAGONA connected to SCADA system RC1 using protocol IEC 60870-5-101.

June 2008

E-mail accounts changed, please visit page Contact.

New accounts:
srcsoft@srcsoft.co.rsaleksandar.vuckovic@srcsoft.co.rs; ...

Registered new domains www.srcsoft.rs and www.rcsoft.co.rs, domain www.rcsoft.co.yunot valid any more.

May 2008
ED Vranje - DMS application connected to SCADA system RC1.

ED Lazarevac - delivered 6 gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link.
TOTAL OF 128 GATEWAYS FOR RECLOSERS DELIVERED

ELEKTROMORAVA POŽAREVAC, subsidiary Petrovac - delivered and put into operation communication gateway for connecting of TAVRIDA reclosers to SCADA system RC1 via GSM network. Now system consists of 6 reclosers.

ED Pirot - delivered and installed system RC1 equipment for TS 35/10kV Temska and TS 35/10kV Visočka Ržana: signal interfacing, distributed RTU and substation computer. Substations will be connected to SCADA system ED Pirot via radio link, using protocol IEC 60870-5-101. System will be put into operation after establishing of radio link.

April 2008
Formally completed connecting of DMS application to SCADA system RC1 in ED Kraljevo, Trstenik, Raška, V.Banja, Jagodina, Ćuprija.

ED Ćuprija - delivered 4 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link.
TOTAL OF 121 GATEWAYS FOR RECLOSERS DELIVERED

March 2008
ED Jagodina - substation computer in TS 110/20/10kV JAGODINA 2 connected to SCADA system RC1 using protocol IEC 60870-5-101.

February 2008
ED Jagodina - delivered 4 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1.
TOTAL OF 117 GATEWAYS FOR RECLOSERS DELIVERED

ED Šabac - installed and put into operation expansion for digital voice recording system - speech automate on additional 8 channels.

December 2007
ED Kraljevo - completed reconstruction and upgrade of system RC1 RTU in TS 35/10kV Jasen (Konarevo), first time installed 1993.

November 2007
Completed connecting of DMS application to SCADA system RC1 in ED Kraljevo, Trstenik, Raška, V.Banja, Jagodina, Ćuprija.

ED Pirot - substation computer in TS 35/10kV PIROT 1 connected to SCADA system ED Pirot via radio link, using protocol IEC 60870-5-101.

October 2007
AD Elektro Doboj - installed and put into operation system RC1 RTU in TS 35/10kV Šamac 1.

ED Jagodina, subsidiary Rekovac - in TS 35/10kV Rekovac installed and put into operation concentrator for connecting of microprocessor protection devices ARTECHE to SCADA system RC1.

ED Ćuprija - put into operation system RC1 RTU in TS 35/10kV Stenjevac.

September 2007
ELEKTROŠUMADIJA Kragujevac - 3 TAVRIDA reclosers connected to SCADA system RC1. Now system consists of 4 reclosers.

August 2007
ED Pirot - in TS 35/10kV Pirot 1 delivered, installed and put into operation substation computer with fiber optic interface for connection to microprocessor protection devices ARTECHE using protocol IEC 60870-5-103.

July 2007
AD Elektro Doboj - installed and put into operation SCADA system for remote monitoring and control of reclosers via GSM network. Sistem consists of 20 reclosers.

June 2007
ELEKTROŠUMADIJA KRAGUJEVAC - installed and put into operation SCADA system RC1 for remote monitoring and control of TAVRIDA reclosers via GSM network. System consists of one recloser, two remote controlled disconnect switches and locators LOK30.

ED Kraljevo - delivered 13 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link.
TOTAL OF 113 GATEWAYS FOR RECLOSERS DELIVERED

ED Kraljevo - delivered signal interfacing rack for TS 35/10kV Jasen in Konarevo.

April 2007
ED Vranje - completed interface installing and connecting of 7 substations equipped with microprocessor protection devices ISKRA to SCADA system RC1 using protocol IEC 60870-5-101.

ELEKTROMORAVA POŽAREVAC, subsidiary Petrovac - installed and put into operation SCADA system RC1 for monitoring and control of TAVRIDA reclosers via GSM network. Now system consists of 5 reclosers.

ED Raška - installed and put into operation RTUs in TS 35/10kV "Brvenik" and TS 35/10kV "Baljevac".

AD Elektro Doboj - delivered 20 devices for control of reclosers via GSM network.
TOTAL OF 100 GATEWAYS FOR RECLOSERS DELIVERED

ELEKTROMORAVA POŽAREVAC, subsidiary Kučevo - installed and put into operation SCADA system RC1 for monitoring and control of TAVRIDA reclosers via GSM network. Now system consists of 6 reclosers.

March 2007
ED Lazarevac - installed and put into operation system for monitoring and control of TAVRIDA reclosers via radio link. System consists of 7 reclosers.

ED Raška - delivered, installed and put into operation 6 communication gateways for connecting of TAVRIDA reclosers via radio link.
TOTAL OF 80 GATEWAYS FOR RECLOSERS DELIVERED

PD Centar - delivered 18 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via GSM network.

ED Niš - delivered and installed System RC1 RTUs for TS 35/10kV „Stevan Sinđelić“ and TS 35/10kV „12. februar“.

January 2007
ED Niš - delivered and installed System RC1 RTUs for TS 35/10kV „Ćele Kula“.

December 2006
ED Lazarevac - delivered 7 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link.
TOTAL OF 56 GATEWAYS FOR RECLOSERS DELIVERED

ED Niš - completed reconstruction work in TS 35/10kV „Ćele Kula“, TS 35/10kV „Stevan Sinđelić“ i TS 35/10kV „12. februar“, for integration in SCADA system.

November 2006
ED Kraljevo - delivered 4 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link.
TOTAL OF 48 GATEWAYS FOR RECLOSERS DELIVERED

ED Cuprija - delivered signal interfacing rack for TS 110/35/10kV Stenjevac.

ED Vrnjačka Banja - delivered 5 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link.

October 2006
We participated at expo part of Second Regional Conference on Power Distribution, CIRED, Zlatibor.

ED Jagodina - delivered 6 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link.
TOTAL OF 39 GATEWAYS FOR RECLOSERS DELIVERED

ED Vranje - Substations Vranje 1, Vladičin Han and Vranjska Banja interfaced to RC1 SCADA system using IEC 60870-5-101/RC1 protocol gateways.

August 2006
AD Elektrokrajina Banja Luka - delivered system with 3 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link.

Minel Automatika - delivered 7 IEC 60870-5-101/RC1 protocol gateways for interfacing substations in area of ED Vranje to System RC1. Substations are equipped with ISKRA protection relays.

May 2006.
In facilities of AD Elektro Doboj following equipment was installed and put into operation:

  • two System RC1 remote units in 10/0.4kV substations
  • two sets of equipment for remote control of TAVRIDA recloser
  • mini RTU for control of sectional vacuum breaker ZW8 at DV 10kV
  • connection via optical cable between distribution centre and substations TS 35/10kV Usora and TS 35/10kV Rudanka as primary control path. Existing radio line will be used as secondary control path.

April 2006.
AD Elektro Doboj - delivered 2 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link and 1 mini RTU for monitoring and control of vacuum breaker ZW8, ChangKai Electrical which was used as section breaker at DV 10kV.

ED Vrnjačka Banja - installed and put into operation 3 communication gateways for connecting of TAVRIDA reclosers to SCADA system RC1 via radio link

ED Jagodina - installed and put into operation one controller for connecting of TAVRIDA recloser to SCADA system RC1 via radio link.

January 2006.
AD Elektro Doboj - delivered system RC1 distributed RTU for substation 10/0.4kV in Doboj.

30.12.2005.
Completed 5 sets of equipment for control of reclosers ordered by ED Vrnjačka Banja. With this sets included, SRC SOFT has shipped 28 sets of TAVRIDA recloser controllers in total.

27.12.2005.
New SCADA server was commissioned in ED Jagodina, with new release of RC1 SCADA V3.1.;

Installed and commissioned previously shipped equipment for PDC Rekovac and two TAVRIDA recloser controllers.

oct.-nov. 2005.
Completed development of telephone exchange power supply controller DNU 24. This was joint project with IRITEL, Belgrade. Test series of 5 pcs was manufactured and shipped for in-field installation.

23.09.2005.
8 digital voice recording systems with automated voice response were installed and commissioned in distribution centers in the area of JP Elektrosrbija, Kraljevo

26.08.2005.
Awarded JUS ISO 9001/2001 in the field of design, development, and maintenance of microcomputing systems and engineering.

01.07.2005.
Finalised details of operational requirements for automated telephone service for ED Trstenik and ED Kraljevo and automated telephone service officially began operation. Telephone numbers: 036/304-304, 037/707-177.

01.06.2005.
TS 110/10kV Preševo was connected to the system of remote monitoring and control RC1 in distribution center ED Vranje. The remote station was previously equipped with a SIEMENS station computer and SCADA system SICAM PCC/WINCC. SCADA – SCADA communication between station computer in TS 110/10kV Preševo and SCADA system RC1 was established, using protocol IEC 60870-5-101.

18.05.2005.
Completed installation of RTU u RP 20kV Orizare, RP 20kV Obzor and TS Centar-2 and connected to the RC1 system of monitoring and control in the distribution center ED Burgas, Bulgaria. Stations were previously equipped with relays SEPAM 1000, manufacturer SCHNEIDER. Communication between RTU and SEPAM relays was established using protocol MODBUS, and RTU was integrated into previously installed SCADA system RC1.

jan.-apr. 2005.
First remote stations of distribution concept RC1M in TS 35/10kV Vranje 2 and TS 110/10kV Niška Banja were installed.